# TradeBidHaus — Full Contractor Job-Costing Formulas, Benchmarks & Reference Tables (https://tradebidhaus.com) ## 1. Core Contractor Estimating Formulas Used Across TradeBidHaus ### A. True Employee Hourly Cost ("Labor Burden") Per Billable Hour - Annual Paid Hours = Paid Weekly Hours × 52 (typically 2,080 hours) - Net Billable Hours = Annual Paid Hours − Paid Holidays/PTO Hours − (Weekly Unbillable Drive/Shop/Supply Hours × Working Weeks) - Total Annual Employer Cost = Base Wages + Employer FICA (7.65%) + FUTA/SUTA + Workers' Compensation Insurance + Health/Retirement Benefits + Service Truck/Fuel/Tool Allowance - True Burdened Cost per Billable Hour = Total Annual Employer Cost ÷ Net Billable Hours - Target Customer Billing Rate = True Burdened Cost per Billable Hour ÷ (1 − Overhead % − Target Net Profit Margin %) ### B. Markup vs. Gross Profit Margin Divisor Formula - Gross Margin Selling Price = Direct Job Cost ÷ (1 − Target Gross Margin Decimal) - Equivalent Markup % Required = Target Gross Margin ÷ (1 − Target Gross Margin) - Key Benchmark: A 25% markup only yields a 20.0% gross margin; a 30% markup yields a 23.08% margin; a 50% markup yields a 33.33% margin; achieving a 30% gross margin requires a 42.86% markup (Cost ÷ 0.70); achieving a 50% gross margin requires a 100% markup (Cost ÷ 0.50). ### C. Commercial Cleaning Monthly Contract Formula (ISSA Production Method) - Hours per Visit = (Cleanable Sq Ft ÷ Facility Sq-Ft/Hr Production Speed) + ((Restroom Fixtures × Minutes per Fixture) ÷ 60) + Extra Detail Hours - Monthly Visits = Visits per Week × 4.3333 weeks/month (52 weeks ÷ 12 months) - Monthly Direct Cost = (Hours per Visit × Monthly Visits × Burdened Hourly Wage) × (1 + Chemicals/Supplies %) - Monthly Flat Contract Bid = Monthly Direct Cost ÷ (1 − Overhead % − Target Margin %) ### D. Progress Billing & Retainage (AIA G702 / G703 Style) - Column G (Total Completed & Stored to Date) = Column D (Previous Applications) + Column E (Work This Period) + Column F (Materials Presently Stored) - Column H (% Complete) = Column G ÷ Column C (Scheduled Value); Balance to Finish = Column C − Column G - Line 6 (Total Earned Less Retainage) = Line 4 (Total Completed & Stored) − Line 5 (Total Retainage Held) - Line 8 (Net Current Payment Due) = Line 6 − Line 7 (Less Previous Net Certificates for Payment) ### E. Prevailing Wage / Davis-Bacon Annualized Fringe Benefit Credit (WH-347) - Allowable Hourly Fringe Credit = Total Annual Bona Fide Employer Benefit Contributions (Health + Pension/401k + Paid Vacation/Holiday + Apprenticeship) ÷ Total Annual Hours Worked Across All Public & Private Jobs (typically 2,080 hours) - Required Cash-in-Lieu of Fringe = Max(0, Required Hourly Fringe Rate − Allowable Hourly Fringe Credit) - Compliant Davis-Bacon Overtime Paycheck Rate = (1.5 × Required Base Hourly Rate) + (1.0 × Cash-in-Lieu of Fringe) ## 2. All Live Calculators & URLs ### True Crew Hourly Cost ("Labor Burden") & Billable Rate Calculator URL: https://tradebidhaus.com/tools/contractor-employee-labor-burden-calculator Summary: See what an employee actually costs you per billable hour on the job—plus the exact hourly rate you must charge to cover overhead and hit your profit margin. How It Works: 1. Start with the worker’s base hourly pay and standard paid hours per week (usually 40 hours, or 2,080 paid hours per year). 2. Subtract paid holidays, vacation/PTO days, and weekly unbillable hours (morning shop load-up, drive time between jobs, supply house runs, and callbacks) to find the real billable hours per year. 3. Add mandatory employer payroll taxes (7.65% FICA, federal FUTA, and state SUTA), trade-specific Workers’ Compensation insurance, health benefits, 401(k) match, and monthly truck/fuel/tool allowances. 4. Divide Total Annual Employer Cost by Net Billable Hours to reveal your True Burdened Cost per Billable Hour—then divide by (1 − Overhead% − Target Profit Margin%) to set your profitable customer billing rate. ### Progress Billing & Retainage Pay-App Worksheet (AIA G702 / G703 Style PDF) URL: https://tradebidhaus.com/tools/construction-progress-billing-and-retainage-calculator Summary: Fill out your line-item Schedule of Values, calculate current draw amounts and retainage withheld, and print a clean 2-page payment application in one click. How It Works: 1. Enter your project details, Application Number, retainage percentages for completed work and stored materials (typically 5% or 10%), and any approved Change Order totals. 2. Fill in each line of your Schedule of Values (Column C: Scheduled Value, Column D: Work Completed from Previous Applications, Column E: Work Completed This Period, and Column F: Materials Presently Stored). 3. The calculator automatically computes Total Completed and Stored to Date (Column G = D + E + F), Percentage Complete (G ÷ C), Balance to Finish (C − G), and Variable Retainage (Column I) on every line. 4. Review the G702-style Application Summary block—which subtracts Total Retainage and Previous Certificates Paid to arrive at your exact Current Payment Due—then click Print / Save PDF. ### Commercial Cleaning & Janitorial Bid Calculator + Client Proposal Maker URL: https://tradebidhaus.com/tools/commercial-cleaning-bid-calculator Summary: Estimate nightly crew hours using real square-foot production rates and restroom fixture counts, then print a client-ready commercial cleaning proposal. How It Works: 1. Select the facility type to load realistic square-foot-per-hour production speeds (e.g., 3,500 sq ft/hr for standard offices, 2,000 sq ft/hr for medical clinics, 2,800 sq ft/hr for schools, or 5,500 sq ft/hr for open warehouses). 2. Add the count of restroom fixtures (toilets, urinals, and sinks). High restroom density slows down production speeds, so pricing fixtures separately at 3 to 4.5 minutes each prevents underbidding. 3. Multiply total hours per visit by Weekly Visits × 4.333 weeks per month (52 weeks ÷ 12 months) and multiply by your True Burdened Crew Hourly Cost. 4. Add chemical/consumable supply allowances, company overhead %, and your target gross profit margin to get your Monthly Flat Contract Price, Per-Visit Price, and effective Price per Square Foot. ### Contractor Markup vs. Gross Profit Margin & Good-Better-Best Quote Builder URL: https://tradebidhaus.com/tools/contractor-markup-vs-margin-quote-calculator Summary: See the exact dollar difference between markup and gross margin on your job costs, and generate a 3-option Good / Better / Best estimate sheet. How It Works: 1. Enter your Raw Materials Cost (plus a waste/fastener allowance %), Total Crew Hours × Burdened Labor Rate, and any Subcontractor, Permit, or Equipment Rental expenses to find your Total Direct Job Cost. 2. Enter your company Overhead % and your Target Gross Profit Margin %. 3. Compare the two columns side by side: Column A shows what happens if you only multiply costs by (1 + % Markup), while Column B divides Job Cost by (1 − Margin%) so you actually keep your full profit target. 4. Use the automatically generated Good / Better / Best 3-Option Quote Builder at the bottom to print a clean proposal sheet for your customer. ### Time & Materials (T&M) + Change-Order Pricing Calculator URL: https://tradebidhaus.com/tools/time-and-materials-and-change-order-calculator Summary: Price mid-job extras, hidden conditions, and T&M service work accurately—and print a formal Change Order Approval Sheet before picking up a hammer. How It Works: 1. Enter the Change Order number, project name, and a clear 1–2 sentence description of the added or modified work. 2. Input your Lead Technician hours, Apprentice/Helper hours, and any after-hours Overtime at your fully burdened billable T&M rates. 3. Add raw material receipts plus your contractual Material Handling & Warranty Markup % (typically 15% to 30%), along with any rental equipment or debris disposal fees. 4. Specify how many calendar days this extra work adds to the project completion date, then click Print / Save PDF to get the customer’s signature before starting. ### Prevailing Wage & Fringe-Benefit Hourly Credit Calculator (Davis-Bacon / WH-347 Helper) URL: https://tradebidhaus.com/tools/prevailing-wage-fringe-benefit-calculator Summary: Calculate your bona fide hourly fringe benefit credits, find the exact Cash-in-Lieu amount owed on the paycheck, and verify compliant Davis-Bacon overtime pay. How It Works: 1. Enter the published Prevailing Wage Base Hourly Rate and Required Hourly Fringe Rate from the project wage determination sheet. 2. Enter the employer-paid bona fide benefits for this worker (monthly health insurance, annual 401(k)/pension contribution, paid vacation/holiday wages, and approved apprenticeship training) plus total annual hours worked across all public and private jobs (typically 2,080 hours). 3. The calculator divides annual employer benefit contributions by total annual hours worked (annualization rule) to determine your Allowable Hourly Fringe Credit. 4. Any shortfall between the Required Fringe Rate and your Allowable Credit becomes Cash-in-Lieu of Fringe paid directly on the paycheck—and the tool computes the exact Davis-Bacon overtime rate (1.5× Base Rate + 1.0× Fringe). ## 3. Flagship Trade Rate Summaries ### Construction Retainage Caps & Release Deadlines by State (50-State Chart) URL: https://tradebidhaus.com/rates/construction-retainage-caps-by-state Summary: Most US states cap construction retainage between 5% and 10% of each progress payment. Today, over 30 states mandate a maximum 5% cap (or step down from 10% to 5% at 50% project completion) on public works, while 24+ states strictly cap private commercial contract retainage at 5% to 10%. ### Workers’ Comp & True Hourly Labor Burden Benchmarks by Trade URL: https://tradebidhaus.com/rates/workers-comp-and-labor-burden-rates-by-trade Summary: Across US construction and field service trades, mandatory employer taxes plus benefits and unbillable drive time add 32% to 82% on top of an employee’s base hourly paycheck. Workers’ Compensation insurance is the largest variable, ranging from ~0.4% for office staff and ~4.1% for commercial cleaning up to ~11.4% for framing carpentry and ~18.5%+ for roofing. ### Commercial Cleaning Production Rates Chart (Sq Ft per Hour by Facility) URL: https://tradebidhaus.com/rates/commercial-cleaning-production-rates-chart Summary: Standard commercial cleaning production rates range from 1,800–2,200 sq ft/hr in high-touch medical and dental clinics, to 3,200–4,000 sq ft/hr in multi-tenant professional offices, up to 5,000–7,000 sq ft/hr in open warehouses. Always add 3.0 to 4.5 minutes per restroom fixture when bathroom density is high. ### Markup to Gross Profit Margin Conversion Chart (10% to 100% Lookup Table) URL: https://tradebidhaus.com/rates/markup-to-gross-margin-conversion-chart Summary: Markup is profit divided by your Job Cost, while Gross Margin is profit divided by your Selling Price. Because your Selling Price is always larger than your Job Cost, a 25% markup only produces a 20.0% gross margin, a 35% markup only produces a 25.9% margin, and a 50% markup produces a 33.3% margin. To achieve a 50% gross margin, you must apply a 100% markup (2.00x multiplier). ## 4. Plain-English Guides Summaries ### Markup vs. Margin for Contractors: Why a 25% Markup Only Leaves a 20% Margin (With Lookup Chart) URL: https://tradebidhaus.com/guides/markup-vs-margin-for-contractors Answer-First Summary: Markup is how much you add to your job cost, while gross margin is the percentage of the final selling price that stays in your pocket after paying direct job costs. Because the final selling price is bigger than your cost, a 25% markup on a $10,000 job ($12,500 bid) only gives you a 20% gross margin ($2,500 ÷ $12,500). To keep a true 25% gross margin, you must divide your cost by 0.75—which requires a 33.3% markup ($13,333.33 bid). ### How to Calculate True Employee Labor Burden in Construction & Field Service (Worked Crew Examples) URL: https://tradebidhaus.com/guides/how-to-calculate-employee-labor-burden-in-construction Answer-First Summary: Employee labor burden is the gap between what you pay a worker per hour on their paycheck and what that worker actually costs your business for every billable hour spent on a customer job. When you include employer payroll taxes (FICA, FUTA, SUTA), Workers’ Compensation insurance, paid holidays/PTO, health benefits, service van expenses, and 5 to 8 weekly unbillable drive/shop hours, a $30/hr field tech typically costs $47 to $56 per billable hour. ### How Progress Billing, Schedule of Values & Retainage Work on Commercial Jobs URL: https://tradebidhaus.com/guides/progress-billing-schedule-of-values-and-retainage-guide Answer-First Summary: Progress billing lets contractors invoice monthly for the exact percentage of work completed and materials stored on site during long projects. Every commercial draw uses two linked sheets: a line-item Schedule of Values (G703 style) tracking percent complete across project phases, and an Application Summary (G702 style) that subtracts 5%–10% retainage and prior net payments to show the exact Current Payment Due. ### How to Price a Commercial Cleaning Contract Per Square Foot Without Underbidding URL: https://tradebidhaus.com/guides/how-to-price-commercial-cleaning-contracts-per-square-foot Answer-First Summary: Typical 5-night-per-week commercial cleaning contracts average $0.11 to $0.18 per square foot per month for standard offices, $0.20 to $0.32/sq ft for medical clinics, and $0.06 to $0.11/sq ft for open warehouses. However, profitable janitorial contractors never bid from a blind square-foot number—they calculate nightly crew hours from facility production speeds (2,000 to 5,500 sq ft/hr) plus restroom fixture counts, multiply by 4.333 weeks/month, and divide by (1 − Overhead% − Profit Margin%).