How Progress Billing, Schedule of Values & Retainage Work on Commercial Jobs

Master the 9 columns of the G703 Schedule of Values, the G702 payment summary math, stored materials billing, and retainage step-down rules.

50-Word Field Answer: Progress billing lets contractors invoice monthly for the exact percentage of work completed and materials stored on site during long projects. Every commercial draw uses two linked sheets: a line-item Schedule of Values (G703 style) tracking percent complete across project phases, and an Application Summary (G702 style) that subtracts 5%–10% retainage and prior net payments to show the exact Current Payment Due.

1. Why Commercial Jobs Use Progress Billing Instead of Simple Invoices

On a two-day residential water heater swap or a small driveway pour, invoicing is simple: you collect a deposit upfront and collect the balance when the truck pulls out of the driveway. But when a commercial general contractor or specialty subcontractor takes on a $180,000 tenant buildout, school wing, or warehouse electrical package that lasts four months, nobody can wait 120 days to get paid—and no property owner or construction lender will hand over 50% upfront without seeing verified progress.

Progress billing solves this by breaking the total contract price into a pre-approved menu of phases called a Schedule of Values (SOV). Once a month—usually on the 20th or 25th—you submit a formal Payment Application showing how much of each line item was finished during that billing period, how much approved material is safely stored on site, and how much retainage (typically 5% or 10%) is being held back in reserve until final punchlist completion.

The construction industry’s universal blueprint for progress billing is the two-page AIA G702® (Application and Certificate for Payment cover sheet) and AIA G703® (Continuation Sheet / Schedule of Values). Even when a contract does not require purchasing branded AIA paper forms, 99% of commercial GCs and banks require your monthly pay app PDF to follow the exact same 9 columns and 9 summary lines.

2. The 9 Columns of the Schedule of Values (G703 Continuation Sheet) Explained

Before you submit Pay Application #1, the General Contractor or Architect will ask for your Schedule of Values. Think of the SOV as your contract price broken into 6 to 20 logical, inspectable chunks of work whose total equals 100% of your Original Contract Sum.

Smart subcontractors always include distinct line items for upfront costs like Mobilization, Submittals/Shop Drawings, and Long-Lead Material Procurement so they can legitimately bill for early administrative and staging expenses on Draw #1 without "front-loading" field installation lines.

Once your SOV is approved, every monthly continuation sheet tracks nine exact columns from left to right. Let’s walk through how each column works and see a real 4-line example table.

Anatomy of a 9-Column G703-Style Schedule of Values Continuation Sheet (Draw #2 Example)
Col A/B: Item & DescriptionCol C: Scheduled ValueCol D: From Previous AppsCol E: This Period WorkCol F: Presently StoredCol G: Total to Date (D+E+F)Col H: % (G÷C) & Bal (C−G)Col I: 10% Retainage
01. Submittals & Mobilization$15,000$15,000$0$0$15,000100% ($0 Bal)$1,500
02. Rough-In Framing & Backing$45,000$30,000$15,000$0$45,000100% ($0 Bal)$4,500
03. Drywall Hang & Level 4 Finish$60,000$0$30,000$6,000$36,00060% ($24,000 Bal)$3,600
04. Acoustical Ceilings & Closeout$30,000$0$0$4,000$4,00013.3% ($26,000 Bal)$400
TOTALS (Must Match G702 Cover)$150,000$45,000$45,000$10,000$100,00066.7% ($50,000 Bal)$10,000
Build & Print Your G702 / G703 Pay App for Free

Our Progress Billing Calculator runs all 9 column formulas and the G702 cover summary automatically—and exports a clean 2-page PDF with zero signup.

Open G702 / G703 Pay-App Calculator →

3. How to Bill for Stored Materials (Column F) Without Getting Rejected

Column F (Materials Presently Stored, Not in D or E) is a lifesaver for cash flow when you have to buy $25,000 worth of electrical switchgear, HVAC rooftop units, acoustical tile, or custom doors weeks before the building is ready for installation. However, Column F is also the #1 spot where subcontractor math breaks on the next month’s draw.

Remember what the word "Presently" in Column F means: it only counts materials sitting in storage at the end of THIS billing period that have NOT yet been installed. Suppose on Draw #2 you bill $6,000 in Column F for drywall sheets delivered and stacked on the second floor. Next month, during Draw #3, your crew hangs all $6,000 of that drywall on the walls.

On Draw #3, that $6,000 moves out of Column F (Stored Materials drops back to $0) and moves into Column D/E (Work Completed)! If you leave the $6,000 sitting in Column F while also billing for hanging the drywall in Column E, you double-bill the line item and your pay app will be kicked back immediately.

Also note that most commercial GCs require three attachments whenever you put a dollar figure in Column F: (1) the vendor invoice proving your actual material cost, (2) a signed delivery ticket or photos showing the materials labeled for the project on site (or in a bonded warehouse with a certificate of insurance), and (3) an itemized stored-material log.

4. The 9 Lines of the G702 Payment Application Cover Sheet

Once your Schedule of Values totals are tallied at the bottom of the continuation sheet, those numbers flow directly onto the G702-style Application Summary cover sheet. Here is how the nine standard lines lock together:

Line 1 (Original Contract Sum): Your base subcontract amount before any change orders ($150,000 in our example above). Line 2 (Net Change by Change Orders): The sum of all fully signed, approved Change Orders to date ($0). Line 3 (Contract Sum to Date): Line 1 plus Line 2 ($150,000)—this must always equal the total of Column C on your Schedule of Values.

Line 4 (Total Completed & Stored to Date): Pulled directly from the total of Column G ($100,000). Line 5 (Retainage): Total retainage withheld on completed work and stored materials to date (10% of $100,000 = $10,000, pulled from Column I). Line 6 (Total Earned Less Retainage): Line 4 minus Line 5 ($100,000 − $10,000 = $90,000 net earned to date).

Line 7 (Less Previous Certificates for Payment): The NET dollar amount certified and paid on all prior pay applications (on Draw #1, $45,000 of work minus $4,500 retainage = $40,500 net certified). Line 8 (Current Payment Due): Line 6 minus Line 7 ($90,000 − $40,500 = $49,500.00 net check due this month). Line 9 (Balance to Finish, Including Retainage): Line 3 minus Line 6 ($150,000 − $90,000 = $60,000 remaining to be paid over the rest of the job, consisting of $50,000 unbilled work plus $10,000 held in retainage).

5. Negotiating Retainage Reductions and Collecting Your Final Check

When a job carries 10% retainage and your net profit margin is 10% to 12%, your entire profit on the project is locked up inside the owner’s retainage account until closeout. Waiting six months after your crew leaves the jobsite to collect retainage puts enormous strain on working capital—especially for early-phase trades like excavation, concrete foundations, steel, and framing who finish their work months before the building gets a Certificate of Occupancy.

Before signing a commercial subcontract, check our 50-State Construction Retainage Caps Table. Over 30 states cap public works retainage at 5% (or mandate a step-down from 10% to 5% once the project is 50% complete), and more than two dozen states now cap private commercial retainage at 5% (including New York on contracts >=$150k, Colorado, Minnesota, Virginia, Utah, and Oregon).

If you are an early-finishing trade on a long project, always request a Line-Item Retainage Release clause stating that your retainage reduces to 5% upon 50% completion of YOUR subcontract scope, and releases in full within 30 days of final inspection of your trade’s work rather than waiting for final tenant landscaping six months later.

6. Monthly Pay Application Submission Checklist (Never Miss a Draw Cutoff)

In commercial contracting, missing the monthly billing cutoff by 24 hours doesn’t mean your check arrives one day late—it usually means your draw gets pushed into next month’s owner funding cycle, delaying your cash by a full 30 days. Build a disciplined monthly billing routine five days before the GC’s cutoff date (typically the 15th to 20th of each month).

Step 1: Walk the site or call the GC’s Project Manager on the 15th to agree on "Pencil Draw" percentages for each Schedule of Values line item before submitting your signed final PDF. When the PM agrees upfront that rough-in is 85% complete and drywall is 40% complete, your official Pay Application sails through approval with zero redlines.

Step 2: Double-check that your Conditional Partial Lien Waiver matches the exact Net Current Payment Due (Line 8) down to the cent, and attach Unconditional Partial Lien Waivers from your own major material suppliers for the previous month’s paid draw.

Step 3: Verify that your Certificate of Insurance (COI), certified payroll reports (if on a prevailing wage project), and signed Change Order logs are current in the GC’s accounting portal so an administrative hold never freezes an approved progress check.

Frequently Asked Questions

What is the most common math mistake on Line 7 (Less Previous Certificates for Payment)?

The #1 error is accidentally typing last month’s GROSS work completed (Column D, before retainage) into Line 7 instead of last month’s NET Earned Less Retainage (Line 6 from the prior pay app). If you subtract prior gross billings AND also subtract total cumulative retainage on Line 5, you subtract your prior month’s retainage twice and shortchange your current check.

Can I put unapproved Change Orders on my G702 / G703 Pay Application?

No. Almost every commercial GC accounting system automatically rejects pay apps that include pending or unexecuted Change Order requests on the Schedule of Values. Only add a Change Order line item to Column C once you hold a counter-signed Change Order number.