Quick Summary: Most US states cap construction retainage between 5% and 10% of each progress payment. Today, over 30 states mandate a maximum 5% cap (or step down from 10% to 5% at 50% project completion) on public works, while 24+ states strictly cap private commercial contract retainage at 5% to 10%.
Launch the matching interactive calculator and export a client-ready PDF worksheet in 1 click.
All 50 US States: Private vs. Public Construction Retainage Caps & Release Rules
| State | Private Contract Cap | Public Works Cap | 50% Completion Step-Down Rule | Typical Final Release Window |
|---|---|---|---|---|
| Alabama | 10% up to 50% complete (5% total) | 5% up to 50% complete (2.5% total) | Zero additional retainage after 50% complete | 30 days after final acceptance |
| Alaska | Per contract (typically 5%–10%) | 10% maximum | Discretionary reduction after 50% complete | 90 days or final acceptance |
| Arizona | 10% maximum | 10% up to 50% complete | Reduces to 5% at 50% completion on public jobs | 60 days after substantial completion |
| Arkansas | 5% maximum | 5% maximum | Capped at 5% throughout project | 30 days after final completion |
| California | Per contract (10% standard) | 5% maximum (standard public) | Public works capped at 5% from day one | 45–60 days after completion |
| Colorado | 5% maximum (private commercial) | 5% maximum | Capped at 5% from start on private & public | 60 days after contract completion |
| Connecticut | 5% maximum | 5% maximum (2.5% on some DOT) | Capped at 5% across commercial & public | 30–60 days after acceptance |
| Delaware | Per contract (typically 5%–10%) | 5% maximum | Public jobs may reduce to 2% after 50% | 30 days after final approval |
| Florida | Per contract (10% common) | 5% maximum | Flat 5% max on public contracts | 30–60 days after punchlist |
| Georgia | 10% (or 5% depending on terms) | 5% maximum (effective 2022+) | Zero additional public retainage at 50% if on track | 30 days after substantial completion |
| Hawaii | Per contract (10% standard) | 5% up to 50% complete (2.5% max) | No retainage withheld after 50% if satisfactory | 60 days after completion |
| Idaho | 5% maximum | 5% maximum | Capped at 5% on both private and public | 30–45 days after completion |
| Illinois | 10% up to 50% complete (5% total) | 10% up to 50% complete (5% total) | Must drop to 5% total retainage at 50% complete | 30 days after final acceptance |
| Indiana | Per contract (5%–10% typical) | 3% to 6% up to 50% complete | No additional public retainage after 50% | 60 days after substantial completion |
| Iowa | Per contract (5%–10% typical) | 5% maximum | Flat 5% cap on public improvements | 30 days after final acceptance |
| Kansas | 10% maximum | 5% maximum (10% if <$100k) | Can reduce if project is on schedule at 50% | 30 days after substantial completion |
| Kentucky | 10% up to 50% complete (5% total) | 10% up to 50% complete (5% total) | Total retainage capped at 5% after 50% milestone | 30–45 days after substantial completion |
| Louisiana | Per contract (5%–10%) | 10% (<$500k) / 5% (>=$500k) | 5% cap on public contracts of $500,000 or more | 45 days after recorded acceptance |
| Maine | 5% maximum | 5% maximum | Capped at 5% on public and private work | 30 days after final completion |
| Maryland | 5% maximum (if 100% bonded) | 5% maximum | Capped at 5% when payment/performance bonds exist | 30–90 days after substantial completion |
| Massachusetts | 5% maximum (projects >$3M) | 5% maximum | Strict 5% cap on private commercial >$3M & public | 30–65 days after substantial completion |
| Michigan | Per contract (10% common) | 10% up to 50% complete (5% total) | No further public retainage after 50% complete | 30–60 days after completion |
| Minnesota | 5% maximum | 5% maximum | Strict 5% statutory ceiling on all contracts | 60 days after substantial completion |
| Mississippi | 5% maximum (or 10% up to 50%) | 5% up to 50% complete (2.5% total) | Steps down to 2.5% overall at 50% complete | 45 days after substantial completion |
| Missouri | 5% maximum (if bonded; else 10%) | 5% maximum (10% if unbonded <$50k) | 5% cap protects bonded subcontractors | 30 days after final acceptance |
| Montana | 5% maximum | 5% maximum | Strict 5% cap across private and public work | 30 days after acceptance |
| Nebraska | 10% up to 50% complete (5% total) | 10% up to 50% complete (5% total) | Drops to maximum 5% total once 50% complete | 45 days after substantial completion |
| Nevada | 5% maximum | 5% up to 50% complete (2.5% total) | Private capped at 5%; public halves at 50% | 30 days after occupancy/notice |
| New Hampshire | Per contract (5%–10% typical) | 5%–10% per agency spec | DOT typically reduces after 50% milestone | 45–60 days after completion |
| New Jersey | Per contract (typically 5%–10%) | 2% maximum (most public agencies) | One of the lowest public retainage caps in the US (2%) | 30–45 days after acceptance |
| New Mexico | Zero retainage allowed by statute | Zero retainage allowed by statute | NM Prompt Pay Act prohibits construction retainage | Prompt payment upon draw approval |
| New York | 5% maximum (private >=$150,000) | 5% maximum (if bonded; 10% unbonded) | 2023 NY law capped private commercial >=$150k at 5% | 30 days after substantial completion |
| North Carolina | Per contract (5%–10%) | 5% up to 50% complete (2.5% total) | No public retainage withheld after 50% complete | 45 days after project acceptance |
| North Dakota | Per contract (typically 5%–10%) | 10% up to 50% complete (5% total) | Zero additional public retainage after 50% | 30–45 days after completion |
| Ohio | Per contract (typically 8%–10%) | 8% on first 50% of work (4% total) | Zero retainage withheld on final 50% of public labor | 30 days after substantial completion |
| Oklahoma | Per contract (5%–10%) | 5% up to 50% complete (2.5% total) | Reduces to 2.5% after 50% completion | 30 days after final completion |
| Oregon | 5% maximum | 5% maximum | Capped at 5%; interest-bearing escrow required >$500k | 30 days after final acceptance |
| Pennsylvania | Per contract (10%->5% common) | 10% up to 50% complete (5% total) | Public retainage must step down to 5% at 50% | 30–45 days after substantial completion |
| Rhode Island | 5% maximum | 5% maximum | Strict 5% cap on private and public contracts | 30–60 days after completion |
| South Carolina | Per contract (10% common) | 3.5% maximum (highway/public) | Low 3.5% public cap; sub retainage cannot exceed GC % | 30–45 days after acceptance |
| South Dakota | Per contract (5%–10%) | 10% or per agency spec | Typically steps down at 50% completion | 30 days after final acceptance |
| Tennessee | 5% maximum | 5% maximum | Mandatory interest-bearing escrow on jobs >=$500k | 90 days after substantial completion |
| Texas | 10% statutory mechanic’s lien reserve | 5% (>=$5M) or 10% (<$5M) | Private owners must hold 10% statutory reserve for 30 days | 30 days after final completion |
| Utah | 5% maximum | 5% maximum | Capped at 5%; sub retainage cannot exceed GC % | 45 days after occupancy/completion |
| Vermont | Per contract (10%->5% typical) | 10% up to 50% complete | Typically reduced to 5% or 0% after 50% complete | 30 days after final acceptance |
| Virginia | 5% maximum (private commercial) | 5% maximum | Both private and public contracts capped at 5% | 30–45 days after final acceptance |
| Washington | Per contract (5% common) | 5% maximum | 5% public cap held in trust for taxes & liens | 45–60 days after DOR/L&I releases |
| West Virginia | Per contract (5%–10%) | 10% up to 50% complete (5% total) | No further public retainage after 50% complete | 45 days after completion |
| Wisconsin | Per contract (5%–10%) | 5% up to 50% complete | Zero additional public retainage after 50% if on time | 30–45 days after acceptance |
| Wyoming | Per contract (5%–10%) | 5% maximum | Flat 5% public works retainage limit | 40 days after notice of completion |
Contractor Estimating & Contract Field Notes
How the 50% Completion Step-Down Rule Works in Practice
In states like Alabama, Illinois, Kentucky, Michigan, Ohio, and Pennsylvania, the owner withholds 10% (or 8% in Ohio) on the first half of the job, and then withholds 0% on the second half as long as work is progressing satisfactorily—bringing effective total retainage down to 5% (or 4%) by substantial completion.
Flow-Down Rule: GC Cannot Hold More Retainage Than the Owner Holds
In almost every state with a retainage cap, a General Contractor is legally prohibited from withholding a higher retainage percentage from a subcontractor than the Property Owner is withholding from the General Contractor.
Frequently Asked Questions
Which state bans construction retainage completely?
New Mexico is the only US state whose Prompt Payment Act generally prohibits withholding retainage on construction contracts, requiring full payment of undisputed progress draws within statutory deadlines.
What did New York’s 5% Private Retainage Law change?
Under New York’s amended General Business Law (effective November 2023), retainage on private commercial construction contracts of $150,000 or more is strictly capped at 5% of the contract sum, and subcontractors cannot be held to more than the percentage withheld from the GC.