Construction Retainage Caps & Release Deadlines by State (50-State Chart)

Compare private commercial and public-works retainage limits, 50%-completion step-down rules, and final payout deadlines across all 50 US states.

Quick Summary: Most US states cap construction retainage between 5% and 10% of each progress payment. Today, over 30 states mandate a maximum 5% cap (or step down from 10% to 5% at 50% project completion) on public works, while 24+ states strictly cap private commercial contract retainage at 5% to 10%.

Run These Rates on Your Own Job Numbers

Launch the matching interactive calculator and export a client-ready PDF worksheet in 1 click.

Open G702 / G703 Progress Billing & Retainage Calculator →

All 50 US States: Private vs. Public Construction Retainage Caps & Release Rules

All 50 US States: Private vs. Public Construction Retainage Caps & Release Rules
StatePrivate Contract CapPublic Works Cap50% Completion Step-Down RuleTypical Final Release Window
Alabama10% up to 50% complete (5% total)5% up to 50% complete (2.5% total)Zero additional retainage after 50% complete30 days after final acceptance
AlaskaPer contract (typically 5%–10%)10% maximumDiscretionary reduction after 50% complete90 days or final acceptance
Arizona10% maximum10% up to 50% completeReduces to 5% at 50% completion on public jobs60 days after substantial completion
Arkansas5% maximum5% maximumCapped at 5% throughout project30 days after final completion
CaliforniaPer contract (10% standard)5% maximum (standard public)Public works capped at 5% from day one45–60 days after completion
Colorado5% maximum (private commercial)5% maximumCapped at 5% from start on private & public60 days after contract completion
Connecticut5% maximum5% maximum (2.5% on some DOT)Capped at 5% across commercial & public30–60 days after acceptance
DelawarePer contract (typically 5%–10%)5% maximumPublic jobs may reduce to 2% after 50%30 days after final approval
FloridaPer contract (10% common)5% maximumFlat 5% max on public contracts30–60 days after punchlist
Georgia10% (or 5% depending on terms)5% maximum (effective 2022+)Zero additional public retainage at 50% if on track30 days after substantial completion
HawaiiPer contract (10% standard)5% up to 50% complete (2.5% max)No retainage withheld after 50% if satisfactory60 days after completion
Idaho5% maximum5% maximumCapped at 5% on both private and public30–45 days after completion
Illinois10% up to 50% complete (5% total)10% up to 50% complete (5% total)Must drop to 5% total retainage at 50% complete30 days after final acceptance
IndianaPer contract (5%–10% typical)3% to 6% up to 50% completeNo additional public retainage after 50%60 days after substantial completion
IowaPer contract (5%–10% typical)5% maximumFlat 5% cap on public improvements30 days after final acceptance
Kansas10% maximum5% maximum (10% if <$100k)Can reduce if project is on schedule at 50%30 days after substantial completion
Kentucky10% up to 50% complete (5% total)10% up to 50% complete (5% total)Total retainage capped at 5% after 50% milestone30–45 days after substantial completion
LouisianaPer contract (5%–10%)10% (<$500k) / 5% (>=$500k)5% cap on public contracts of $500,000 or more45 days after recorded acceptance
Maine5% maximum5% maximumCapped at 5% on public and private work30 days after final completion
Maryland5% maximum (if 100% bonded)5% maximumCapped at 5% when payment/performance bonds exist30–90 days after substantial completion
Massachusetts5% maximum (projects >$3M)5% maximumStrict 5% cap on private commercial >$3M & public30–65 days after substantial completion
MichiganPer contract (10% common)10% up to 50% complete (5% total)No further public retainage after 50% complete30–60 days after completion
Minnesota5% maximum5% maximumStrict 5% statutory ceiling on all contracts60 days after substantial completion
Mississippi5% maximum (or 10% up to 50%)5% up to 50% complete (2.5% total)Steps down to 2.5% overall at 50% complete45 days after substantial completion
Missouri5% maximum (if bonded; else 10%)5% maximum (10% if unbonded <$50k)5% cap protects bonded subcontractors30 days after final acceptance
Montana5% maximum5% maximumStrict 5% cap across private and public work30 days after acceptance
Nebraska10% up to 50% complete (5% total)10% up to 50% complete (5% total)Drops to maximum 5% total once 50% complete45 days after substantial completion
Nevada5% maximum5% up to 50% complete (2.5% total)Private capped at 5%; public halves at 50%30 days after occupancy/notice
New HampshirePer contract (5%–10% typical)5%–10% per agency specDOT typically reduces after 50% milestone45–60 days after completion
New JerseyPer contract (typically 5%–10%)2% maximum (most public agencies)One of the lowest public retainage caps in the US (2%)30–45 days after acceptance
New MexicoZero retainage allowed by statuteZero retainage allowed by statuteNM Prompt Pay Act prohibits construction retainagePrompt payment upon draw approval
New York5% maximum (private >=$150,000)5% maximum (if bonded; 10% unbonded)2023 NY law capped private commercial >=$150k at 5%30 days after substantial completion
North CarolinaPer contract (5%–10%)5% up to 50% complete (2.5% total)No public retainage withheld after 50% complete45 days after project acceptance
North DakotaPer contract (typically 5%–10%)10% up to 50% complete (5% total)Zero additional public retainage after 50%30–45 days after completion
OhioPer contract (typically 8%–10%)8% on first 50% of work (4% total)Zero retainage withheld on final 50% of public labor30 days after substantial completion
OklahomaPer contract (5%–10%)5% up to 50% complete (2.5% total)Reduces to 2.5% after 50% completion30 days after final completion
Oregon5% maximum5% maximumCapped at 5%; interest-bearing escrow required >$500k30 days after final acceptance
PennsylvaniaPer contract (10%->5% common)10% up to 50% complete (5% total)Public retainage must step down to 5% at 50%30–45 days after substantial completion
Rhode Island5% maximum5% maximumStrict 5% cap on private and public contracts30–60 days after completion
South CarolinaPer contract (10% common)3.5% maximum (highway/public)Low 3.5% public cap; sub retainage cannot exceed GC %30–45 days after acceptance
South DakotaPer contract (5%–10%)10% or per agency specTypically steps down at 50% completion30 days after final acceptance
Tennessee5% maximum5% maximumMandatory interest-bearing escrow on jobs >=$500k90 days after substantial completion
Texas10% statutory mechanic’s lien reserve5% (>=$5M) or 10% (<$5M)Private owners must hold 10% statutory reserve for 30 days30 days after final completion
Utah5% maximum5% maximumCapped at 5%; sub retainage cannot exceed GC %45 days after occupancy/completion
VermontPer contract (10%->5% typical)10% up to 50% completeTypically reduced to 5% or 0% after 50% complete30 days after final acceptance
Virginia5% maximum (private commercial)5% maximumBoth private and public contracts capped at 5%30–45 days after final acceptance
WashingtonPer contract (5% common)5% maximum5% public cap held in trust for taxes & liens45–60 days after DOR/L&I releases
West VirginiaPer contract (5%–10%)10% up to 50% complete (5% total)No further public retainage after 50% complete45 days after completion
WisconsinPer contract (5%–10%)5% up to 50% completeZero additional public retainage after 50% if on time30–45 days after acceptance
WyomingPer contract (5%–10%)5% maximumFlat 5% public works retainage limit40 days after notice of completion

Contractor Estimating & Contract Field Notes

How the 50% Completion Step-Down Rule Works in Practice

In states like Alabama, Illinois, Kentucky, Michigan, Ohio, and Pennsylvania, the owner withholds 10% (or 8% in Ohio) on the first half of the job, and then withholds 0% on the second half as long as work is progressing satisfactorily—bringing effective total retainage down to 5% (or 4%) by substantial completion.

Flow-Down Rule: GC Cannot Hold More Retainage Than the Owner Holds

In almost every state with a retainage cap, a General Contractor is legally prohibited from withholding a higher retainage percentage from a subcontractor than the Property Owner is withholding from the General Contractor.

Frequently Asked Questions

Which state bans construction retainage completely?

New Mexico is the only US state whose Prompt Payment Act generally prohibits withholding retainage on construction contracts, requiring full payment of undisputed progress draws within statutory deadlines.

What did New York’s 5% Private Retainage Law change?

Under New York’s amended General Business Law (effective November 2023), retainage on private commercial construction contracts of $150,000 or more is strictly capped at 5% of the contract sum, and subcontractors cannot be held to more than the percentage withheld from the GC.