| Line Item / Phase | Scope Description & Specifications | Qty / % | Unit Rate / Scheduled | Line Total |
|---|---|---|---|---|
| 01. Demo & Site Protection | Ram Board floor protection, dust barrier, demo existing tub surround & vanity, haul debris | 1 LS | $1,850.00 | $1,850.00 |
| 02. Rough Plumbing & Shower Valve | Install new pressure-balanced mixing valve, relocate 2" shower drain, pressure test | 1 LS | $2,140.00 | $2,140.00 |
| 03. Waterproofing & Tile Shower Surround | 1/2" cement board + liquid membrane waterproofing + porcelain wall/floor tile up to ceiling | 115 SF | $48.00/SF | $5,520.00 |
| 04. 60" Double Vanity, Quartz Top & Trim | Set solid-wood vanity cabinet, undermount bowls, faucets, GFCI circuit, and LED mirror | 1 LS | $4,390.00 | $4,390.00 |
| 05. Frameless 3/8" Tempered Glass & Paint | Custom heavy glass enclosure + 2 coats moisture-resistant satin enamel on walls/ceiling | 1 LS | $2,950.00 | $2,950.00 |
Contract Terms, Notes & Payment Schedule
- Payment Draw Schedule: 30% Deposit upon contract signing ($5,055.00), 40% upon rough-in & waterproofing inspection ($6,740.00), 30% upon substantial completion ($5,055.00).
- Proposal Validity: Prices quoted are guaranteed for 30 calendar days from proposal date. Hidden structural rot, mold, or code violations behind walls will be priced via written Change Order prior to proceeding.
- Workmanship Warranty: Contractor provides a 2-year written labor warranty in addition to all manufacturer material warranties.
The above prices, specifications, and conditions are satisfactory and are hereby accepted. Contractor is authorized to perform the work as specified.
Prepared and submitted in good faith based on visible site conditions and stated specifications.
Estimator Checklist Before Printing or Sending This Form
- Verify your total job price uses Gross Margin division [Cost ÷ (1 − Margin%)] rather than simple markup.
- List explicit exclusions (e.g., structural engineering, asbestos abatement, or permit fee pass-throughs) so scope boundaries are crystal clear.
- Include a milestone payment draw schedule tied to physical inspection stages rather than vague calendar dates.
Load this exact worksheet preset inside our interactive calculator to adjust crew hours, taxes, or retainage percentages automatically.
Frequently Asked Questions
Should I show individual material and labor hours on a customer estimate?
For fixed-price residential and light commercial bids, show clear scope phases (e.g., Demo, Rough-In, Tile Installation, Finish Trim) with a lump-sum price per phase rather than exposing your raw hourly wage and material receipts. That gives the customer full clarity on what is included without inviting line-by-line hardware-store haggling.
What is the safest deposit percentage for a contractor estimate?
A 25% to 35% deposit upon signing covers upfront material orders and locks in the schedule. Be sure to check your state home-improvement law—for example, California caps upfront down payments on residential home improvement at 10% or $1,000 (whichever is less) before work starts.