Signed Construction Change-Order Approval Form

Document mid-job scope additions, material upgrades, and completion date extensions, then print a clean sign-off PDF before starting extra work.

Document Code: TBH-CO-302 (Editable in Browser)
Open in Interactive Calculator
CONSTRUCTION CHANGE ORDER & CONTRACT AMENDMENT
Project: 2nd Floor Bath & Laundry Remodel — Change Order #CO-02
Client / Owner: Property Owner / GC: Marcus & Elena Vance
Contractor: Contractor: Your Remodeling & Carpentry LLC
Ref: TBH-CO-302
Date: 2026-11-20
Click any text or cell below to edit before printing
Editable Line-Item Scope & Pricing Schedule (Click Any Cell to Customize)
Line Item / Phase Scope Description & Specifications Qty / % Unit Rate / Scheduled Line Total
Lead Carpenter Labor (Demo & Joist Sistering) Remove rotted subfloor, sister (4) 2x10 joists with structural ledger locks, install blocking 10.0 Hrs $95.00 / Hr $950.00
Apprentice / Helper Labor Material staging, debris carry-out to roll-off container, fastener installation 10.0 Hrs $62.00 / Hr $620.00
Materials + 25% Sourcing & Warranty Markup (4) 2x10x12 KD Fir joists, (3) sheets 3/4" Advantech T&G subfloor, subfloor adhesive & screws ($485 raw) 1.25x $485.00 $606.25
Debris Disposal & Hauling Fee (+15%) Additional landfill weight & haul trip for water-damaged wood/tile subbase 1.15x $165.00 $189.75

Contract Terms, Notes & Payment Schedule

  • Payment Terms for Change Order: 100% of this Change Order ($2,366.00) is due upon signing [or billed with the next scheduled progress draw].
  • Authorization: Work described in this Change Order shall not commence until signed by Owner/Authorized Agent below. All other terms of the original Contract remain in full force and effect.
Original Contract Sum (Plus Prior Approved COs) $28,500.00
Net Addition This Change Order (#CO-02) +$2,366.00
New Revised Total Contract Sum $30,866.00
Contract Schedule Impact / Completion Extension +2 Working Days
CLIENT / OWNER / GC ACCEPTANCE

The above prices, specifications, and conditions are satisfactory and are hereby accepted. Contractor is authorized to perform the work as specified.

Authorized Client Signature & Date
CONTRACTOR AUTHORIZED REPRESENTATIVE

Prepared and submitted in good faith based on visible site conditions and stated specifications.

Contractor Signature, Title & Date

Estimator Checklist Before Printing or Sending This Form

  • Take clear timestamped jobsite photos of the concealed condition before covering it up.
  • Fill in the exact number of calendar or working days added to the completion schedule.
  • Get a signature (or written email confirmation referencing the Change Order PDF number) before ordering materials.
Want Automatic Math & Live Margin Checks?

Load this exact worksheet preset inside our interactive calculator to adjust crew hours, taxes, or retainage percentages automatically.

Open in Interactive Calculator →

Frequently Asked Questions

When should a Change Order be billed?

On residential remodeling jobs, require 50% to 100% payment of the Change Order upon authorization so you never finance mid-job upgrades out of pocket. On commercial subcontracts, approved Change Orders are added to your Schedule of Values and billed on the current month’s G702/G703 Pay Application.

What if we don’t know the exact hours required until demo is finished?

Issue the Change Order with a clearly stated Time & Materials hourly rate (e.g., $95/hr Lead Tech + $62/hr Helper + Materials at Cost + 25%) and a Not-to-Exceed check-in cap, then attach daily T&M tickets.