G702 / G703 Progress Draw & Schedule of Values Worksheet

Edit your Schedule of Values line items and retainage draw summary right below, or open in the full Progress Billing Calculator.

Document Code: TBH-PAYAPP-702 (Editable in Browser)
Open in Interactive Calculator
APPLICATION AND CERTIFICATE FOR PROGRESS PAYMENT (G702 / G703 STYLE)
Project: Oakridge Medical Suite 200 Tenant Buildout (Contract #SC-2026-118)
Client / Owner: To (Owner / General Contractor): Apex Commercial Builders LLC
Contractor: From (Subcontractor): Summit Interior Systems Inc. • Draw #3
Ref: TBH-PAYAPP-702
Date: 2026-11-20
Click any text or cell below to edit before printing
Editable Line-Item Scope & Pricing Schedule (Click Any Cell to Customize)
Line Item / Phase Scope Description & Specifications Qty / % Unit Rate / Scheduled Line Total
01. Mobilization & Submittals 100% Complete • $12,000 Prev / $0 This Period 100.0% $12,000.00 $12,000.00
02. Interior Metal Stud Framing 100% Complete • $45,000 Prev / $0 This Period 100.0% $45,000.00 $45,000.00
03. Rough-In Coordination & Sound Batt 100% Complete • $18,000 Prev / $10,000 This Period 100.0% $28,000.00 $28,000.00
04. Drywall Hang, Level 4 Tape & Finish 84.6% Complete • $11,500 Prev / $28,500 Current / $4,000 Stored 84.6% $52,000.00 $44,000.00
05. Acoustical Ceiling Grid & Tile 54.4% Complete • $0 Prev / $12,000 Current / $6,500 Stored 54.4% $34,000.00 $18,500.00
06. Doors, Frames, Hardware & Closeout 0.0% Complete • Balance to Finish: $24,000.00 0.0% $24,000.00 $0.00

Contract Terms, Notes & Payment Schedule

  • Contractor Certification: The undersigned Contractor certifies that to the best of the Contractor’s knowledge and belief, the Work covered by this Application for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid by the Contractor for Work for which previous Certificates for Payment were issued and payments received, and that current payment shown herein is now due.
  • Attach conditional partial lien waiver for current draw ($54,900.00) and unconditional partial lien waiver for prior paid draw ($77,850.00).
Total Completed & Stored to Date (Column G) $147,500.00
Less 10.0% Retainage Held to Date (Column I) −$14,750.00
Less Previous Net Certificates Approved (Draws #1–#2) −$77,850.00
NET CURRENT PAYMENT DUE THIS APPLICATION $54,900.00
CLIENT / OWNER / GC ACCEPTANCE

The above prices, specifications, and conditions are satisfactory and are hereby accepted. Contractor is authorized to perform the work as specified.

Authorized Client Signature & Date
CONTRACTOR AUTHORIZED REPRESENTATIVE

Prepared and submitted in good faith based on visible site conditions and stated specifications.

Contractor Signature, Title & Date

Estimator Checklist Before Printing or Sending This Form

  • Submit your draft Schedule of Values for approval before the first billing cycle so line items are balanced.
  • Include invoices and delivery packing slips whenever billing for Column F (Materials Presently Stored on site).
  • Verify that Line 3 (Contract Sum to Date) includes only fully executed, signed Change Orders.
Want Automatic Math & Live Margin Checks?

Load this exact worksheet preset inside our interactive calculator to adjust crew hours, taxes, or retainage percentages automatically.

Open in Interactive Calculator →

Frequently Asked Questions

When do commercial general contractors require G702 / G703 progress billing forms?

Almost every commercial subcontract over $25,000 requires monthly progress billing on or before the 20th or 25th of the month using a Schedule of Values table and an Application Summary cover sheet.

How do I bill for retainage release at the end of a commercial project?

Once your work achieves Substantial Completion and punchlist sign-off, submit a dedicated Final Retainage Pay Application where Completed Work is 100% and Retainage % is set to 0%, releasing the accumulated retainage balance as Current Payment Due.