G702 / G703 Progress Draw Schedule
Standard 9-column Schedule of Values continuation sheet and Application for Payment summary cover page.
Fill out your line-item Schedule of Values, calculate current draw amounts and retainage withheld, and print a clean 2-page payment application in one click.
| A. Item | B. Description of Work | C. Scheduled Value ($) | D. Previous Apps ($) | E. Work This Period ($) | F. Stored Mat. ($) | G. Total to Date ($) | H. % / Balance | I. Retainage ($) | Del |
|---|---|---|---|---|---|---|---|---|---|
| $12,000.00 | 100.0% ($0) | $1,200.00 | |||||||
| $45,000.00 | 100.0% ($0) | $4,500.00 | |||||||
| $28,000.00 | 100.0% ($0) | $2,800.00 | |||||||
| $44,000.00 | 84.6% ($8,000) | $4,400.00 | |||||||
| $18,500.00 | 54.4% ($15,500) | $1,850.00 | |||||||
| $0.00 | 0.0% ($24,000) | $0.00 | |||||||
| SCHEDULE OF VALUES TOTALS | $195,000.00 | $86,500.00 | $50,500.00 | $10,500.00 | $147,500.00 | 75.6% ($47,500) | $14,750.00 | ||
| 1. ORIGINAL CONTRACT SUM (Sum of Column C Scheduled Values) | $195,000.00 |
| 2. Net Change by Approved Change Orders | $8,500.00 |
| 3. CONTRACT SUM TO DATE (Line 1 ± Line 2) | $203,500.00 |
| 4. TOTAL COMPLETED & STORED TO DATE (Column G Total on G703) | $147,500.00 |
| 5. RETAINAGE (Total of Column I on G703 Continuation Sheet) | −$14,750.00 |
| 6. TOTAL EARNED LESS RETAINAGE (Line 4 Less Line 5) | $132,750.00 |
| 7. LESS PREVIOUS CERTIFICATES FOR PAYMENT (Prior Net Approved Draws) | −$77,850.00 |
| 8. CURRENT PAYMENT DUE THIS APPLICATION (Line 6 Less Line 7) | $54,900.00 |
| 9. BALANCE TO FINISH, INCLUDING RETAINAGE (Line 3 Less Line 6) | $70,750.00 |
The undersigned Contractor certifies that to the best of the Contractor’s knowledge, the Work covered by this Application has been completed in accordance with the Contract Documents and that current payment shown herein is now due.
In accordance with the Contract Documents, based on on-site observations and the data comprising this application, the Owner/GC certifies that the Work has progressed as indicated and Applicant is entitled to payment of the Amount Certified.
A drywall subcontractor has a $200,000 base contract with 10% retainage. On Pay App #1 they billed $60,000 of work (receiving $54,000 net after $6,000 retainage). On Pay App #2 they complete another $50,000 of work and store $10,000 of verified materials on site.
| Cost / Billing Line Item | Formula / Basis | Dollar / Hour Result |
|---|---|---|
| 1. Original Contract Sum (+ $0 Change Orders) | Base Schedule of Values total | $200,000.00 |
| 2. Total Completed & Stored to Date (Col G) | $60,000 prev + $50,000 current + $10,000 stored | $120,000.00 |
| 3. Retainage Held to Date (10% of Col G) | 10% × $120,000 total completed & stored | $12,000.00 |
| 4. Total Earned Less Retainage | $120,000.00 − $12,000.00 | $108,000.00 |
| 5. Less Previous Certificates for Payment | Net paid on Pay Application #1 | $54,000.00 |
| 6. Current Payment Due (Pay App #2) | $108,000.00 − $54,000.00 | $54,000.00 |
| 7. Balance to Finish, Including Retainage | $200,000.00 − $108,000.00 earned net | $92,000.00 |
Key Field Takeaway: Over 80% of rejected subcontractor pay apps fail because Column G + Balance to Finish does not match the Contract Sum or because previous gross billings are subtracted instead of previous net certificates.
Yes. While some contracts specifically mandate purchasing copyrighted AIA® paper forms, most commercial general contractors, lenders, and property owners accept standard G702/G703-formatted Schedule of Values spreadsheets and PDFs as long as the 9 columns, retainage math, and notarized/signed certification block match.
Column D on the continuation sheet is the GROSS dollar amount of work completed on prior pay apps before retainage was taken out. "Less Previous Certificates for Payment" on the cover summary is the NET dollar amount already certified/paid after retainage was subtracted.
Simply change the Retainage % on Completed Work input from 10% to 5% (or 7.5% blended if your contract only reduces retainage on the second half of the job). The calculator updates Total Retainage Held to Date and releases the excess into your Current Payment Due.
Standard 9-column Schedule of Values continuation sheet and Application for Payment summary cover page.
Written Change Order form documenting added scope, labor & material cost, revised contract total, and schedule extension.
Private vs. public construction retainage percentage caps, 50% step-down milestones, and statutory release deadlines across all 50 states.
How to structure your Schedule of Values, avoid rejected G702/G703 monthly draw applications, and collect held retainage.