| Line Item / Phase | Scope Description & Specifications | Qty / % | Unit Rate / Scheduled | Line Total |
|---|---|---|---|---|
| Journeyman Wireman — Regular Hours | J. Ramirez • Run (2) 3/4" EMT conduits from Panel LP-2 to MDF server racks & pull #10 THHN | 8.0 Hrs | $115.00 / Hr | $920.00 |
| Apprentice Electrician — Regular Hours | T. Brooks • Assist conduit bending, J-box mounting, and scissor lift spotter | 8.0 Hrs | $72.00 / Hr | $576.00 |
| Overtime Crew Hours (After 3:30 PM Cutover) | Panel shutdown, breaker termination & megger circuit testing (1.5x billable tier) | 4.0 Hrs | $140.25 / Hr | $561.00 |
| Materials Installed (+20% Handling Markup) | 80 ft 3/4" EMT, couplings, (2) L6-30R twist-lock receptacles, 500 ft #10 THHN, (2) 30A 2P breakers ($640 raw) | 1.20x | $640.00 | $768.00 |
| 19-Ft Electric Scissor Lift Daily Allocation (+15%) | High-bay ceiling conduit routing allocation | 1 Day | $109.25 | $109.25 |
Contract Terms, Notes & Payment Schedule
- Field Superintendent Verification: Signature below confirms that the labor hours, personnel, and materials listed above were furnished on site on this date. If T&M rates are governed by master subcontract, accounting will apply approved schedule rates.
The above prices, specifications, and conditions are satisfactory and are hereby accepted. Contractor is authorized to perform the work as specified.
Prepared and submitted in good faith based on visible site conditions and stated specifications.
Estimator Checklist Before Printing or Sending This Form
- Have the GC superintendent sign the physical or tablet PDF ticket at the end of the shift—never wait until the end of the month.
- Attach supply-house packing slips or photos of material labels used from truck stock.
- Separate straight-time hours from overtime hours clearly.
Load this exact worksheet preset inside our interactive calculator to adjust crew hours, taxes, or retainage percentages automatically.
Frequently Asked Questions
What if the GC superintendent refuses to sign a T&M ticket with dollar prices on it?
Many commercial superintendents are only authorized to verify "Time and Quantities" (hours worked and materials installed) while the Project Manager verifies pricing in the office. Having the superintendent sign off on the physical hours and material list still locks in 95% of your claim.
How soon should signed T&M tickets be converted into a formal Change Order?
Submit your signed daily T&M tickets to the Project Manager within 48 to 72 hours (most commercial subcontracts have a strict 5-day or 7-day notice window for extra work claims).