See what an employee actually costs you per billable hour on the job—plus the exact hourly rate you must charge to cover overhead and hit your profit margin.
| Cost / Hour Component | Annual Total | Per Billable Hr |
|---|---|---|
| Net Billable Hours vs. Paid Hours | 1,617 / 2,080 hrs | 77.7% Billable |
| 1. Gross Annual Base Wages | $66,560.00 | $41.16/hr |
| 2. Employer Payroll Taxes (FICA + FUTA/SUTA) | $6,988.80 | $4.32/hr |
| 3. Workers’ Compensation Insurance | $3,461.12 | $2.14/hr |
| 4. Health Insurance & Retirement Match | $7,756.80 | $4.80/hr |
| 5. Service Truck, Fuel & Tool Allowance | $7,800.00 | $4.82/hr |
| Total Employer Cost (True Labor Burden) | $92,566.72 | $57.25/hr |
A service contractor pays a lead tech $30.00/hr for 40 hours a week (2,080 paid hours/year). The tech gets 10 paid days off (80 hrs) and spends 6 hours a week driving, loading materials, and doing paperwork (300 hrs/year). That leaves only 1,700 billable hours on customer jobs.
| Cost / Billing Line Item | Formula / Basis | Dollar / Hour Result |
|---|---|---|
| Base Annual Wages | 2,080 paid hrs × $30.00/hr | $62,400.00 |
| Employer Payroll Taxes (FICA + FUTA/SUTA) | 10.5% × $62,400 | $6,552.00 |
| Workers’ Comp & General Liability Allocation | 6.5% × $62,400 | $4,056.00 |
| Health Insurance & Retirement Match | $450/mo + 3% match | $7,272.00 |
| Service Van, Fuel, Uniforms & Small Tools | $600/mo × 12 months | $7,200.00 |
| Total Annual Cost to Employ Worker | Sum of wages, taxes, benefits & truck | $87,480.00 |
| True Burdened Cost per Billable Hour | $87,480 ÷ 1,700 billable hours | $51.46 / hr |
| Target Customer Hourly Rate (18% OH + 22% Profit) | $51.46 ÷ (1 − 0.40) | $85.77 / hr |
Key Field Takeaway: At $30/hr on the paycheck, this tech actually costs the company $51.46 for every billable hour on a jobsite. Charging $45/hr loses $6.46 every single hour before office overhead is even paid!
For most W-2 construction and field service employees, total labor burden runs between 35% and 70% on top of base hourly pay when measured against billable hours. Low-hazard trades like cleaning or clerical work sit around 28%–38%, while high-workers-comp trades like carpentry and roofing often reach 55%–80%.
You pay your crew for 40 hours a week, but you can only bill customers for the hours spent actually building or repairing. If a tech spends 7.5 hours a week driving between calls, picking up parts, and cleaning the van, you are spreading 40 hours of wages and benefits across only 32.5 billable hours—which raises your true hourly labor cost by 23% immediately.
Either method works as long as you never leave it out. Most field service and remodeling contractors assign dedicated van, gas card, and hand-tool allowances directly to the lead tech’s hourly burden so multi-day labor-heavy bids automatically cover fleet costs.
Never use simple markup if you want a true profit margin. Divide your True Burdened Hourly Cost by (1 − Overhead % − Target Gross Profit %). For example, if your burdened cost is $50/hr and you need 20% for office overhead plus 20% net profit (40% total), divide $50 by 0.60 to get $83.33/hr.
Daily jobsite T&M log sheet with crew hours, material receipts, equipment rental, and GC superintendent sign-off.
Internal job-costing worksheet breaking down W-2 base pay into true cost per billable hour and profitable customer rates.
Side-by-side comparison of Workers’ Comp rates and total labor burden multipliers for Electrical, HVAC, Carpentry, Roofing, Cleaning, and more.
Instant lookup chart converting target Gross Profit Margin % into required Markup % and Multiplier on $1k, $10k, and $50k job costs.
Why a 25% markup only leaves a 20% gross margin, how overhead eats underpriced bids, and the exact divisor table for every job size.
Complete breakdown of employer payroll taxes, trade workers comp, PTO, service trucks, and unbillable windshield time with worked crew tables.